Hi all,

We are scheduled to promote and contribute 4.16 RC1 to the simrel on
Friday the 29th.

Don't forget to consult the endgame plan regarding release candidates:
https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_16.php

Here is the schedule:

Wednesday 27 May -- API and feature freeze, Release Candidate build
Thursday 28 May -- Bug verification and Sign-off 4.16 RC1
Friday 29 May -- 4.16 RC1 Promotion and contribution to SimRel

Please note the following excerpt from the freeze plan:

RC1
All fixes submitted must have a project lead or PMC vote on the bug
report, and the fix must be reviewed by an additional committer (any
committer other than the one who made the fix). A positive review from
a project lead or PMC member means implicit approval and no vote is
needed on the bug report. Ongoing changes to documentation, tests or
examples do not require approval.